The director of the
Aspen-Pitkin County Airport is moving on to another facility, but
planning for the future will continue well beyond Jim Elwood’s tenure.
On Tuesday, the outgoing
aviation director shared with Pitkin County commissioners the timing of
proposed improvements to Sardy Field, which could be phased over the
next decade.
Replacing the existing
commercial terminal is top priority in the master planning process, and
within the next 30 days, a grant application will be submitted to the
Federal Aviation Administration that could cover the costs of an
environmental assessment. The EA, a required step to gauge a project’s
impacts, may take up to two years to complete.
According to JD Ingram of
the consulting firm Jviation, the FAA’s ongoing involvement in planning
the future of Aspen’s airport will be helpful when competing for grant
allocations.
“The FAA makes economic
decisions based on priority rankings. When you have the FAA reps
themselves at the table, they see the value in it,” Ingram said.
In early 2015, the FAA is
scheduled to begin reviewing Sardy Field’s airport layout plan, which
could potentially include a new runway design. Elwood said more runway
space is needed in the future to accommodate jets with wingspans wider
than 95 feet. By 2021, half of the current fleet will be retired, and
all of the current commercial jets are to be taken out of service by
2025.
In terms of the proposed
timeline for airport improvements, Elwood stressed, “The board and the
community control this timeline to the extent they want.” He also said
that a decision to move forward “doesn’t mean we have to build that
item.”
That seemed to provide some comfort to Commissioner Rachel Richards.
“Our community,
rightfully so, has a lot of concerns about change and growth ... and
this ultimately is a lot of change and construction over the next seven
or eight years,” she said.
Commissioner Rob Ittner
wants to reserve the county’s right to consider “a small
re-verification” if new information comes forward from an airline or
aircraft manufacturer that could nullify the need for a runway to
accommodate planes with wing spans of up to 115 feet.
Runway relocation
wouldn’t be finished until midway through 2022, according to the initial
schedule. And that would allow airport officials time to consider a
change.
“It’s really prudent we
continue to cross-check the information,” said Elwood, who recently
announced he is leaving Aspen, after 13 years, to take the airport
manager’s job in Jackson, Wyo.
During the next six
months, outreach efforts will be designed to inform the public about the
Future Air Service Planning Study, which includes redeveloping the
terminal area, possibly reconfiguring the runway and considering an
additional private aviation center. In July, commissioners approved
$219,000 for outreach efforts.
The terminal area
improvement has already been approved by the FAA as part of the
airport’s 2012 master plan. It impacts circulation on the airfield,
parking and the current private aviation center. The lease for the
current fixed-based operator, Atlantic Aviation, expires in 2023.
After the project’s
environmental assessment is complete, there’s a six-month window to
study all aspects of the plan in the hopes of gaining what is known as a
“FONSI” (finding of no significant impact).
“Once you have that FONSI
in the process, you can start the design of the terminal,” said Ingram.
Its construction could take up to four years, with completion targeted
around the end of 2021.
Community input will be
key to planning for a potential runway expansion that could encroach
onto Owl Creek Road and the contiguous Burlingame Ranch open space
parcel. Studies have determined that moving the existing runway 80 feet
to the west and widening it by 150 feet could help bring the airport up
to FAA standards.
Elwood said this facet is still under evaluation and will be revisited after the community has a chance to weigh in on the plan.
The expansion would also
allow room for a second fixed-based operator for general aviation, which
Elwood indicated would likely happen. Landmark Aviation has submitted
an application, and others are anticipated.
Early estimates target the airfield expansion to cost at least $121 million.
“We have a need to share
with the community what these pieces mean to us,” said Elwood. He asked
commissioners to remember how important public transparency is to the
process.
Ittner agreed that the
public should be a part of the ongoing discussion so there are no
misunderstandings. For example, it could take a year to construct a new
runway but not all of the work would be done at once. Instead, the
construction could be completed during offseason and night closures of
the runway.
“We don’t want anyone to think a year of construction means the runway is going to be closed for a year,” said Ittner.
- Source: http://www.aspendailynews.com
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment