At the Wednesday, Oct. 9
meeting of the Transportation and Highway Committee, Price County
Airport Manager Brian Ernst discussed a change in plans to correct a
drainage problem on the airport’s south end.
An infiltration
basin designed to collect runoff and drain within 24 to 48 hours was
modified in the process of removing materials from the area to provide
base material for a hangar space. It had been assumed that the
depression would continue to drain as it had previously, but after the
work was completed, the depression began collecting water much like a
pond, only evaporating very slowly, as Ernst explained.
As a temporary fix, Ernst has been running a pump to keep the water level down whenever he’s at the airport, he said.
The geese that had been congregating there seem to have moved on, in Ernst’s observations.
He reported that he had been creating noise to scare away the geese, which present a potential strike danger at airports.
Rather
than move forward with the original plan of putting a new drainage
point in the nearby city storm sewer, it looks like construction
contractors will be recontouring the ground and pulling the topsoil
back. Corrective steps are set to take place in the week ahead, Ernst
reported.
The initial estimate for that work came in at $11,500
and should be factored into the total cost of the current Airport
Improvement Project through a change order.
Ernst said that he
approached the Bureau of Aeronautics about the matter, feeling that it
seemed like an engineering mistake and that someone should be held at
least somewhat accountable for the extra expense.
The response
from the Bureau was that there are things that can’t be foreseen when
moving forward with such projects, according to Ernst, who noted that
this kind of issue is something of “an odd duck,” and hasn’t come up in a
lot of similar projects.
Since the topsoil seems to be acting
like a seal for the basin, Ernst said that he’s going to request it be
left off once it’s removed.
Committee member and Price County
Supervisor Jim Hintz suggested that the simplest fix might be creating a
French drain about the size of the table they were gathered around with
layers of easily infiltrated materials like sand and rock.
Construction
aspects of the Airport Improvement Project (AIP) have come to a
standstill in order to give subgrade and soft spots on surfaces a chance
to firm up.
The electrical contractor is still working at the airport off and on, Ernst said.
Tree
clearing work on properties where easements have been successfully
negotiated is set to go ahead in November, according to Ernst.
The
overall project contractor will likely get estimates from other
contractors and if figures look good, tree clearing will be handled
through a change order without putting the work out for a separate bid,
as Ernst explained.
For the stretch of land along Elk Lake Drive,
an arborist is working with the city to establish a report on how the
cutting will need to be done in order to be in line with a municipal
tree ordinance.
Negotiations for an easement continue on parcel
39. The owners have decided to seek out their own appraisal to compare
with the one that came in from Bureau negotiators, as Ernst explained.
He
said that officially time probably ran out for the second appraisal,
though the Bureau appears to be making an exception to try and work
through the deal with the property owners without having to resort to
condemnation in the courts.
Ernst reported that he hasn’t been
able to get a drop-dead date from the Bureau in regards to when the
negotiation has to be settled.
Committee Chairman Larry Palecek said that sooner or later, they need to stop delaying the inevitable and settle the matter.
Ernst
discussed major topics coming out of the dialogue at an airport and
land use seminar he had attended along with the airport operations
technician in the end of September. One big topic centered on the
arrival of visits to assess potential wildlife dangers at airports in
2015. Airports where potential wildlife interactions are identified will
be required to individually bring in biologists and work out a plan for
mitigating hazards. For the sake of not only cost savings but
efficiency and consistency, Ernst and other airport managers are trying
to get the Bureau on board with a statewide program to supply expert
guidance rather than leaving it up to airports to find it.
Committee
members gave the okay for the airport to bring back the air show and
fly-in event held each 4th of July weekend so long as Harbor View is on
board with it and again co-sponsoring it.
In business items,
committee members approved renewing the five-year lease on Marquip’s
hangar space and changing the name on the lease to 4 Seasons Community
Development LLC, which is managing the rental agreement for the
corporation.
Read more: http://www.pricecountydaily.com
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment