Frederick Municipal Airport (KFDK), Maryland: Runway to be painted in the spring

Originally published March 01, 2013

Frederick Municipal Airport's runway will get a face-lift in the first week of April, airport manager Kevin Daugherty said.

The runway markings will be repainted by Speidel Construction, which won a nearly $123,000 contract for the job last summer.

The Virginia company has been waiting out the winter weather to maintain the runway, Daugherty said.

The project is part of routine maintenance at the airport, he said, adding that the last time the markings were repainted was about 2007.

Additionally, the old markings are obsolete since the air control tower was constructed last year, an executive summary of the bid noted.

-- Kelsi Loos