The town of Taos says
it’s ready to break ground on a major expansion at the regional airport,
but it’s now waiting on approval from the Taos County Planning
Department.
“We don’t have a firm
timeline until we get the permit from the county,” said airport manager
John Thompson in an interview Wednesday (Oct. 8). “The federal, state
and local money is all in place. The contractor has his notice of award.
We’re ready.”
However, earlier this
week, the town gave the county permission to take extra time to make a
preliminary decision on the permit application for the project.
Under the county’s land
use regulations, the planning director must determine if an application
for a development permit includes all the necessary documents within 30
days of its submittal. The town filed its original application in early
September, and a decision on whether the it was complete was originally
due this week.
However, in an Oct. 6
email, Taos Town Manager Rick Bellis said the town is willing to waive
the 30-day review requirement because of “the large amount of material”
submitted with the application.
On Sept. 9, the town
council voted to award a construction contract on the first phase of the
project. That 3-2 vote came after weeks of public debate on whether the
expansion was warranted.
The $23 million airport
expansion includes the construction of a second runway meant to improve
safety at the relatively high-altitude airport. Most of the project is
being funded with a federal grant, but the town must come up with a 5
percent match (or about $1.4 million) to receive funding.
Proponents of the project
say modernizing the airport will improve public safety, not only for
private pilots but for the entire community. However, critics have
offered a variety of arguments against the expansion, ranging from fears
that the new runway will increase air traffic, exacerbate Taos’ wealth
gap, or invite more of a military presence in the area. There have also
been concerns that the town has more pressing needs to which it should
be investing its money.
One group of opponents
pointed out that the town had not, until recently, made any attempts to
get zoning approval from Taos County. A lawsuit making those kinds of
allegations was filed Sept. 8 in district court in Taos, around the same
time the town first met with county officials and submitted a permit
application. There has been no movement in that case since it was filed.
The county planning
department is accepting comments on the expansion, though county
officials have said only comments from adjacent landowners will be
weighed in making a final determination on the project.
As of Wednesday (Oct. 7)
the county had received a handful of comments on the proposed expansion,
though it’s not clear at this point how many of those comments are from
adjacent property owners.
- Source: http://www.taosnews.com
No comments:
Post a Comment